Morere 2D Seismic
Project
Morere 2D Seismic Drilling Project
Project type
Seismic shot hole drilling, Explosive loading, Multi-terrain drilling operations
Date
March - April 2013
Location
New Zealand
Client
Southeast Asian Exploration (for NZ Energy Corporation)
Highlight
984 — Total shot holes drilled
10,743 m — Total drilling depth
35 days — Project completion time
Webster Drilling & Exploration was contracted by Southeast Asian Exploration to carry out the drilling and loading programme for the East Coast 2D seismic survey for NZ Energy Corporation. The project required drilling 986 shot holes across challenging terrain in the Marumaru and Morere areas.
Operating from a staging area near Morere Tea Rooms & Camp, the project utilised a combination of helicopter-portable rigs and tractor-mounted equipment to access difficult terrain across five seismic lines. The crew successfully completed 984 of the 986 planned holes, demonstrating exceptional project execution in demanding conditions.
Webster Drilling’s versatile fleet and experienced personnel delivered this complex seismic drilling programme on schedule and within budget, utilising specialised heli-portable equipment and innovative drilling techniques.